Free NASCLA Practice Questions
10 free, exam-style NASCLA (NASCLA) practice questions with answers and
explanations. No signup required. Work through them below, then take the
full free NASCLA practice test to study every exam domain.
Question 1
A contractor's total job cost is $60,000. The owner of the firm wants the project to yield a 25% profit margin on the final contract price. What contract price must the contractor quote to achieve that margin?
- $80,000
- $75,000
- $72,000
- $78,000
Show answer & explanation
Correct answer: A - $80,000
Question 2
An employee must enter a 6-foot-deep trench in Type C soil to make a pipe connection. Which statement correctly reflects the OSHA requirement governing the sloping of this excavation?
- No protective system is required because the trench is shallower than 8 feet
- Sloping is not allowed at this depth; only shoring or a trench shield is permitted
- A protective system is required, and Type C soil is sloped no steeper than 1.5:1 (horizontal:vertical)
- A protective system is required, and Type C soil is sloped no steeper than 0.75:1 (horizontal:vertical)
Show answer & explanation
Correct answer: C - A protective system is required, and Type C soil is sloped no steeper than 1.5:1 (horizontal:vertical)
Question 3
An owner will reimburse the contractor for the actual cost of the work plus a fixed fee, but also wants assurance that the total project cost will not exceed an agreed-upon ceiling. Which contract arrangement BEST meets both of these requirements?
- Cost-plus with a guaranteed maximum price
- Stipulated lump sum based on complete plans
- Unit price tied to measured field quantities
- Time and materials billed at published rates
Show answer & explanation
Correct answer: A - Cost-plus with a guaranteed maximum price
Question 4
A continuous footing is 24 feet long, 30 inches wide, and 12 inches deep. How many cubic yards of concrete are required to place it, before adding any waste allowance?
- 60.0 cubic yards
- 3.3 cubic yards
- 2.2 cubic yards
- 1.8 cubic yards
Show answer & explanation
Correct answer: C - 2.2 cubic yards
Question 5
On a commercial project, a subcontractor properly completes its work but is never paid by the general contractor. Which surety bond is specifically intended to protect that subcontractor's right to payment?
- The bid bond submitted with the proposal
- The performance bond held by the owner
- The payment bond furnished for the project
- The contractor's license bond on file
Show answer & explanation
Correct answer: C - The payment bond furnished for the project
Question 6
In a CPM schedule, one activity has an early start of day 10 and a late start of day 14, while the overall project duration is unchanged. What does this difference tell the project manager about that activity?
- It lies on the critical path and therefore cannot be delayed at all
- It carries 4 days of float and may slip up to 4 days without delay
- It is currently 4 days behind schedule and must be expedited now
- It must begin by day 10 or liquidated damages will be assessed
Show answer & explanation
Correct answer: B - It carries 4 days of float and may slip up to 4 days without delay
Question 7
A specification requires the mortar with the HIGHEST compressive strength for a structural, load-bearing masonry wall. Which mortar type should the mason use?
- Type M
- Type S
- Type N
- Type O
Show answer & explanation
Correct answer: A - Type M
Question 8
A new exterior ramp is being constructed to provide accessible entry to a commercial building. According to the accessibility standard, what is the MAXIMUM running slope permitted for the ramp run?
- 1:8 (steepest allowed for new construction)
- 1:10 (allowed for short rises only)
- 1:12 (one inch of rise per foot of run)
- 1:20 (below this, it is not a ramp)
Show answer & explanation
Correct answer: C - 1:12 (one inch of rise per foot of run)
Question 9
A glazed panel sits in a hazardous location next to a door. The contractor needs safety glazing that, if broken, holds together and stays in the opening instead of falling out as fragments. Which glazing product BEST satisfies this requirement?
- Tempered glass, which breaks into small cubes
- Laminated glass, with an interlayer bonding the panes
- Annealed glass, with no special heat treatment
- Float glass, cut to size from standard stock
Show answer & explanation
Correct answer: B - Laminated glass, with an interlayer bonding the panes
Question 10
A material supplier has not been paid for goods delivered to a commercial jobsite and plans to secure the debt by filing a mechanic's lien. Which statement reflects a fundamental principle the supplier must observe?
- A lien may be filed any time the debt is unpaid, with no statutory deadline
- Statutory notice and filing deadlines apply, or the lien right can be lost
- Only the general contractor, not a supplier, may ever assert lien rights
- Filing the lien by itself guarantees payment without further court action
Show answer & explanation
Correct answer: B - Statutory notice and filing deadlines apply, or the lien right can be lost